An award of $665,000 in damages and legal expenses to a developer in Pacifica has been thrown out by the Ninth U.S. Circuit Court of Appeals. The unanimous three-judge panel determined that a questionable condition of project approval that the city eventually repealed did not constitute a violation of the developer's equal protection rights because the condition did not stop the project from moving forward.
The Ninth Circuit determined that the City of Pacific owed developer North Pacifica LLC nothing.
The case illustrates, Judge Mary Schroeder wrote bluntly, "the friction that can grow between a developer trying to secure approval of a condominium project as quickly as possible, and a city trying to use development permit procedures to avoid all foreseeable future problems."
Pacifica is a city of about 40,000 people on the coast of San Mateo County where slow-growth politics predominate. For more than 25 years, Pacifica's growth wars have spilled into the courts and voting booths. Ten years ago, Pacifica was the setting for the important state appellate court ruling Milagra Ridge Partners Ltd. v. City of Pacifica, 62 Cal.App.4th 108 (1998) (see CP&DR Legal Digest, April 1998). In that case, the court ruled that voters' decision to overturn a general plan amendment permitting a housing subdivision did not amount to inverse condemnation because the developer had never submitted an application that conformed to the general plan. In May of this year, a different developer wanting to develop the "Quarry" property — where voters have blocked development multiple times — sued the city, alleging construction of a water treatment plant and realignment of Calera Creek damaged the property.
The case at hand involved proposed development of a 4.3-acre parcel known as the "Bowl." In 1999, North Pacifica (NP) filed an application for a condominium project on the site. City officials made a number of requests for additional information before finally deeming the application complete in June 2001. Before the application made it to the Planning Commission, North Pacifica sued, alleging that city processing delays had violated the company's due process and equal protection rights.
The Planning Commission approved the project, but a citizen appealed to the City Council. In August 2002, the City Council approved the project subject to 39 conditions of approval. North Pacifica objected to a number of the conditions, including condition 13 (b) requiring that condominium owners be individually and collectively liable for maintenance of building exteriors, landscaping, common areas and an access road. North Pacifica contended that no other condo developer in the state had ever been subject to condition 13 (b) and said it would render the project unsaleable. Apparently, however, North Pacifica's written objections never reached either the Planning Commission or City Council until after the project was approved. At the time, city attorneys and planners insisted on the condition as protection because North Pacifica had filed a different lawsuit in state court demanding that the city maintain the access road. (North Pacifica eventually lost that suit at the appellate court level in 2005.)
A citizen appealed the City Council's approval of the entire project — 19 houses and 24 condominium units on the 5.8 acres as the "Fish" and "Bowl" sites — to the Coastal Commission. Those proceedings ground on for years before the Commission in May 2006 overturned the city's approval because of impacts to wetlands. The developer's suit against the Coastal Commission is pending in state court.
Meanwhile back in federal court, U.S. Magistrate Judge Edward Chen ruled that North Pacifica could not pursue its due process claim because it had not sought compensation in state court. But in October 2003, Judge Chen concluded that imposition of condition 13 (b) did violate the developer's right to equal protection. After that ruling, the City Council repealed the condition. Still, North Pacifica sought damages, and in May 2005 Chen awarded $156,000 in damages, $454,000 in attorney's fees and $55,000 in costs. Chen concluded that the development was worth less from August 2002 until November 2003, the period during which condition 13 (b) was in effect.
Both sides appealed to the Ninth Circuit. North Pacifica sought to resurrect its due process claim, while the city sought to overturn the award for violation of equal protection. The city won on both counts.
The Ninth Circuit concluded that imposition of condition 13 (b) did not violate equal protection rights because there was no evidence the city singled out NP for discriminatory treatment. The court also noted that compensation was not justified unless the developer could prove actual damages.
"The problem" wrote Judge Schroeder, "is that there was no reduction in value attributable to condition 13 (b) because development could not go forward until NP obtained a development permit from the Coastal Commission. The condition did not cause any actual delay. Even if we were to agree that NP should have prevailed on the equal protection claim, it would have been entitled only to nominal damages."
On the due process claim, the Ninth Circuit upheld the district court's ruling but on different grounds. The district court said NP first had to press and lose a claim in state court before seeking relief in federal court. That would have been true had NP filed a taking claim, but the developer instead filed a due process claim based on the city's lengthy process, the Ninth Circuit pointed out.
The Ninth Circuit found there was a "reasonable explanation" for every delay. The city needed additional information to review the application, it sought a new application when NP's agent dropped out of the process, and it restarted the environmental review process after determining that NP wrongly claimed the project was exempt, the court noted.
The Case: North Pacifica LLC v. City of Pacifica, No. 05-16069, 08 C.D.O.S. 5685. Filed May 13, 2008. The Lawyers: For North Pacifica: Jaquelynn Pope, (310) 379-3410. For the city: Lee Rosenthal, Goldfarb & Lipman, (510) 836-6336.
An appellate court has reinstated a lawsuit over environmental review of a recreational trail proposed to be built in San Mateo County.
A Santa Clara County Superior Court judge had thrown out the suit because it was filed after the California Environmental Quality Act's usual 30-day statute of limitations expired. However, the Sixth District Court of Appeal ruled there was "reasonable probability" environmentalists could show that a 180-day statute of limitations applied here.
In the first decision of its kind, a divided Ninth U.S. Circuit Court of Appeals panel has declared that the City of Goleta's mobile home rent control ordinance constitutes a regulatory taking.
A Butte county landowner who claimed that flood control measures undertaken and approved by Butte County amounted to inverse condemnation had all of his arguments rejected by the Third District Court of Appeal. The court ruled that the strict liability standard that applies in most inverse condemnation cases does not apply in the flood control context. Instead, the court determined a rule of reasonableness applied to the claims, and the landowner did not prove that the county acted unreasonably.
A state appellate court has upheld the Coastal Commission's handling of a housing project appeal. The court ruled that although the Commission did not comply precisely with the state open meeting law's requirements, the Commission came close enough and did not portray an intent to avoid the law.
A property owner's challenge of a Sierra Madre City Council resolution directing a committee to consider stricter regulation of hillside development has been thrown out by the Second District Court of Appeal.
The unanimous three-judge appellate panel upheld a trial court judge who had ruled that the situation was not "ripe" for judicial review. Although the resolution might lead to less potential development, the resolution itself had no binding implications for the property owner's land, the Second District determined.
The Ninth U.S. Circuit Court of Appeals continued to flesh out its property rights jurisprudence with a decision from Spokane, Washington — this time by siding with property owners seeking to protect their own rights by enforcing historic preservation regulations.
A property owner challenging the constitutionality of an inclusionary housing ordinance may not employ the nexus and rough proportionality tests from the Nollan and Dolan cases, the Second District Court of Appeal has ruled.
A Contra Costa County order directing a water ski club to remove 28 unpermitted dwelling units plus docks and accessory structures has been upheld by the First District Court of Appeal.
Despite the fact that some of the structures have been in place for 40 years, the county has the authority to order their removal, the court ruled. The court rejected the ski club's argument that the abatement order was a taking of private property and violation of constitutional rights, and the court denied the club's request to limit the county's abatement order.
The Sierra Club's challenge of the environmental review for a large annexation by the City of Orange and a related development by the Irvine Company has been rejected by the Fourth District Court of Appeal.
The court turned away arguments that the environmental analysis for the Santiago Hills and East Orange projects improperly described the project, segmented environmental reviews, failed to adequately address water quality, incorrectly analyzed traffic and lacked a proper project alternatives analysis.
A plan that alters regulations for the operation of a wastewater treatment plant that disposes of effluent into a Sierra Nevada foothills creek, rather than requiring improvements to the plant, has been upheld by the First District Court of Appeal.
Anglers and environmentalists sued over the plan, arguing state water quality regulators violated the California Environmental Quality Act and the Porter-Cologne Water Quality Control Act. But a unanimous three-judge panel of the First District, Division One, ruled for the government.
The California Supreme Court has upheld three timber harvest plans that an appellate court had found to be in violation of the state Forest Practices Act and the California Department of Forestry's functional equivalent of the California Environmental Quality Act. The state high court ruled the analysis of cumulative impact on two rare species was adequate, as was an analysis of likely herbicide use.
The City of Half Moon Bay has reached a settlement agreement with a developer who won a takings lawsuit against the city. Last December, U.S. District Court Judge Vaughn Walker awarded developer Charles Keenan $36.8 million in damages, plus interest and attorney's fees, because an incomplete city drainage project had transformed an approved 24-acre housing project site into an unbuildable wetland (see CP&DR In Brief, January 2008).